Refinery Overhaul Plan
Year:2009 ISSUE:10
COLUMN:ENERGY
Click:216 DateTime:Apr.08,2009
Refinery Overhaul Plan
Refinery Beginning day Target Unit Capacity (million t/a)
Sinopec Jinan Refinery
April 1st (for 30 days) atmospheric and vacuum distillation unit 2.4
Sinopec Changling Petrochemical Company
mid-April (for 40 days) atmospheric and vacuum distillation unit 3.5
mid-April (for 40 days) catalytic cracking unit 1.2
Sinopec Qilu Petrochemical Company
mid-April (for 30 days) atmospheric and vacuum distillation unit 4.0
Sinopec Guangzhou Petrochemical Company
May (for 30 days) atmospheric and vacuum distillation unit 8.0
Sinopec Wuhan Petrochemical Company
May catalytic cracking unit 1.0
PetroChina Liaoyang Petrochemical Company
May whole refinery 5.5
Sinopec Zhenhai Refining & Chemical Company
late May (for 30 days) atmospheric and vacuum distillation unit 9.0
late May (for 30 days) catalytic cracking unit 3.0