Technical Renovation in Tianjin Soda Plant Completed
Year:1999 ISSUE:37
COLUMN:OTHER
Click:225 DateTime:Jan.04,2006
Technical Renovation in Tianjin Soda Plant Completed
Tianjin Soda Plant has used a tied loan of 33 mil-lion U.S.
dollars from the Asian Development Bank and in nearly 3
years completed the major technical renovation to the
existing equipment.
The plant passed the energy renovation project evaluation
conducted by the Asian Development Bank at the end of 1996
and was approved to use a tied loan of 33 million U. S.
dollars from the bank. At the same time, the plant also
got a technical renovation loan of 66.32 million yuan from
the Communication Bank of China.
The renovation was launched on Dec. 18, 1996 and fully
completed in October this year. The capacity of argon is
expanded by 3 600 t/a and the capacity of methanol is
expanded by 45 000 t/a. The technical renovation has
effectively increased the technical content and market
share of Tianjin Soda Plant .