15 000 T/A Carbon Black Project Accepted in Qingzhou
Year:1998 ISSUE:29
COLUMN:OTHER
Click:325 DateTime:Jan.04,2006
15 000 T/A Carbon Black Project Accepted in Qingzhou
The 15 000 t/a carbon black project using the new
technology of wet process prilling has passed acceptance
in Qingzhou Chemical Industrial Co., Ltd.. It is a major
technical renovation project in Shandong. All indexes
reach the design requirements. The planned fixed asset
investment is 53.04 million yuan and the actual investment
is 44. 58 million yuan. The production line already
produced 8 809 tons of carbon black before the acceptance.